* Also asks irrigation development corporations to fix accountability of
officials concerned in cases of delay in completion of irrigation
projects
By Kartik Lokhande
Once bitten, twice shy. Water Resources
Department (WRD) appears to be following this principle as far as the
works of irrigation projects is concerned. After drawing flak for
multi-crore ‘Irrigation Scam’ in the past couple of years, WRD has now
asked Chief Engineers to issue ‘no irregularity’ certificate.
Deputy Secretary (WRD) S D Kulkarni has issued a communication to this
effect to Executive Directors of various irrigation development
corporations in the State, on August 7. As per the communication, Chief
Engineers of various projects and establishments under irrigation
development corporations have to submit a ‘no irregularity certificate’
to Executive Director of respective corporation. The said certificate
should make it clear that all the Government norms have been followed
while executing the work of respective project.
However, not many in the WRD have welcomed this. A senior officer said
that this clause of ‘no irregularity certificate’ has been included to
hold accountable the respective Chief Engineer if anything goes wrong
about a project in future. “Once again, it is officials only who may be
held responsible for following directions of political bosses, which are
many times not issued in writing,” said another officer.
The latest communication of WRD also asks the Executive Directors of
various irrigation development corporations to fix responsibility of
officials concerned if there is delay in completion of an irrigation
project. These clauses have been included in the communication about
approval to execution of remaining work of 64 identified irrigation
projects in the State which are nearing completion. The communication
has been issued to Executive Directors of Vidarbha Irrigation
Development Corporation (VIDC), Maharashtra Krishna Valley Development
Corporation (MKVDC), Tapi Irrigation Development Corporation (TIDC),
Godavari Marathwada Irrigation Development Corporation (GMIDC), and
Konkan Irrigation Development Corporation (KIDC).
These clauses have been introduced in the wake of recommendations of
Special Inquiry Team (SIT) headed by eminent water expert Dr Madhavrao
Chitaley into the multi-crore irrigation scam that had rocked the State
and the country in the year 2012. The latest communication also asks the
officers to approve expenditure after considering the recommendations
of SIT regarding policy and project-level issues. Besides, the
information regarding expenditure incurred, number of projects
completed, creation of actual water storage, irrigation potential
created etc has to be furnished to Funds Allocation Committee headed by
Additional Chief Secretary (Planning).
Approval to exdpenditure to
complete 42 projects in Vid
Meanwhile,
to curtail the delay in completion of 64 identified projects, WRD has
asked the authorities concerned and VIDC, TIDC, MKVDC, GMIDC, and KIDC
to ensure that these projects are completed as per the priority fixed.
Of these, as many 42 projects are in Vidarbha region.
Work has been completed between 75 per cent and 90 per cent in case of
at least 23 of these 64 projects. The estimates of many projects is
under the process of upward revision due to cost escalation. However, it
takes time to get the revised administrative approval for many
projects. Till then, the work cannot be stopped. Hence, WRD has granted
approval to completion of these projects by the time the revised
administrative approval is received.
Of total 64 projects, as many as 42 are in Vidarbha region. These
include a major project Bawanthadi, and five medium projects namely
Wagholi Buti, Karajkheda, Kalpathri, Pothra Nala, Jhansinagar. The
remaining of 42 Vidarbha projects are minor irrigation projects. These
include Bhivgaon, Gogaon, Bahada, Chandsura, Kawranala, Paoni, Ranpisa,
Dharpimpri, Gaiwal, Kasola, Koyali, Kinkhed, Parwakohar, Yewta, Bangaon,
Digdoh, Wai storage tank, Bhimdi, Bor Nadi, Raigad Nadi, Samdasaudali,
Shivangaon, Takli Kalann, Jhatamjhari, Popatkheda-2, Kuttardoh, Swasin,
Lower Dnyanganga-2, Borkhedi, Dahegaon Gargoti, Jamnala, Mahagaon,
Masrul, Vidrupa, Lakhmapur, and Bhuratola.
(09-08-14)
Comments
Post a Comment