Maharashtra scraps work orders of Rs 600 cr, to conduct special audit of power companies
* Guardian Ministers to head committees for respective districts and
monitor functioning of power companies, MLAs to head tehsil-level
committees
By Kartik Lokhande
Maharashtra Government will be
conducting special and independent audit of State-run power utilities
namely Maharashtra State Electricity Distribution Company Limited
(MSEDCL), Maharashtra State Power Generation Company Limited
(Mahagenco), and Maharashtra State Electricity Transmission Company
Limited (Mahatransco).
Chandrashekhar Bawankule, Energy Minister,
made this announcement in Legislative Assembly on Friday. Further, he
announced, work orders to the tune of Rs 600 crore issued during the
tenure of erstwhile Democratic Front (DF) Government would be scrapped.
“The work orders have been scrapped as it has come to the notice of the
Government that these were issued to the contractors at higher rates
than the tender amount,” he said.
 |
| Chandrashekhar Bawankule |
Talking to ‘The Hitavada’ over
telephone, Bawankule said that the work orders were scrapped in case of
16 tenders. “All the work orders were issued on a single date, and all
were issued at rates higher than the tender amount by 10 per cent to 15
per cent. All the tenders pertained to works in MSEDCL,” he said.
It
may be recalled here that a day ago, Radhakrishna Vikhe-Patil, Leader
of Opposition and senior Congress leader, had alleged that there was
rampant corruption in State-run power companies especially in 15 years.
Interestingly, for most of these years of Congress-NCP rule, Ajit Pawar,
senior NCP leader, was the Energy Minister. Vikhe-Patil alleged that on
a single date a company’s tender worrth Rs 4,372 crore was cleared.
Despite infrastructure plan of Rs 950 crore, an additional amount of Rs
850 crore was spent. A huge amount of Rs 700 crore was simply waived by
charging only one per cent penalty. Payment was released to a company
though it did not install capacitors, alleged Vikhe-Patil.
Replying
to the debate on Friday, Bawankule announced in Legislative Assembly
that committees will be constituted at district and tehsil levels to
monitor the functioning of power companies. Guardian Minister will head
district-level committee while MLA will head tehsil-level committee. The
district-level committee will have MLAs, Members of Parliament, and
Mayor as members. Chief Engineer will be the Member Secretary of
district-level committee.
The Energy Minister was replying to
allegations of Radhakrishna Vikhe-Patil, Leader of Opposition, that
there was corruption in the State-run power companies. Vikhe-Patil
sought CBI probe into the matter, to which Bawankule said that probe and
special audit would be conducted but there was no need for CBI probe. A
‘milestones chart’ of the three State-run power companies would be
prepared to ensure that projects were completed on time, he said.
Further, he added, work orders with higher rates would be scrapped.
Bawankule
informed the House that the total debt burden on Mahagenco,
Mahatransco, and MSEDCL was Rs 55,058 crore. Admitting that there were
several ‘issues’ in Energy Department, he assured that within two years
he would effect radical changes in the functioning of State-run power
companies.
3,230 MW generation projects
to be completed by June 2016
Against
the backdrop of increasing demand of power, the projects with
generation capacity of 3,230 MW will be completed by June 2016, said
Chandrashekhar Bawankule. Thesee projects are at Koradi, Chandrapur, and
Parali. Considering ever-increasing demand for power, more power
projects with generation capacity of 5,000 MW will have to be taken up
by the year 2025, he said.
Due to shortage of coal in last two
years, thermal power projects with generation capacity of 1,805 MW were
stalled, the Energy Minister said. Besides, he said, private power
projects with generation capacity of 1,506 MW including the one at
Dabhol were non-functional due to failure in executing the power
purchase agreement (PPA). How to revive these projects would be
discussed with Mahagenco and National Thermal Power Corporation (NTPC)
soon.
Priority to sewage-based
power generation
To
secure power generation for future requirements, Bawankule said,
priority would be accorded to generation of power by using sewage from
municipal corporations in the State. This will secure water supply
required for power projects. It may be mentioned here that Nagpur
Municipal Corporation (NMC) has signed an agreement for sale of sewage
to Mahagenco.
‘No additional burden of
higher tariff on consumers’
MSEDCL
has submitted a proposal to Maharashtra Electricity Regulatory
Commission (MERC) regarding hike in power tariff by 8 per cent. However,
Energy Minister said, consumers will not be burdened with higher
tariff. For the purpose, State Government will ensure that transmission
and distribution losses of State-run power utilities are checked.
Further,
to reduce transmission and distribution losses, pre-paid meters will be
installed and efforts will be made to bring down the losses to 15-16
per cent by the year 2015-16, said Bawankule. Referring to the issue of
12,000 villages not having feeder connection and facing load-shedding,
he said that a feeder separation programme would be taken up and a
proposal was sent to the Centre for financial assistance. In the second
phase, 14,000 villages with single feeder will be taken up, he added.
State
is exploring options of alternative power generation. Accordingly, a
Solar Power Generation Policy to tap generation potential of 14,400 MW
will be placed before the State Legislature soon, he added.
Backlog of 5 lakh agricultural pumps
in Vidarbha, Marathwada regions
Energy
Minister informed the House that there was a backlog of energisation of
five lakh agricultural pumps in Vidarbha and Marathwada regions. This
backlog will be removed by December 2016 and a Rs 1,000 crore scheme
will be launched for the purpose. Besides, the Central Government had
approved 7,540 solar agricultural pumps for Maharashtra. In areas that
have witnessed farmers’ suicides, these solar pumps would be provided if
beneficiaries pay only 5 per cent of the cost, he said. He added that
all District Collectors and Agriculture Officers had been asked to
prepare a list of beneficiaries.
Bar, dhaba to have
pre-paid power meter
Taking
cognisance of reports that power theft/pilferage was rampant at beer
bars and dhaba (road-side eateries), Energy Department will be
installing pre-paid power meters there. If power theft/pilferage comes
to the fore at bar/dhaba, fine would be recovered on the spot, said
Bawankule.
(Filed on March 20, 2015)